Flexible budgets and variance analysis

Bridge static budget to actual results

Static uses planned activity and standard rates. Flexible uses actual output and standard rates. Keep fixed costs at budgeted levels within the relevant range. Volume variance = flexible − static. Performance variance = actual − flexible. Their sum is total variance = actual − static. Higher costs are unfavourable. Higher revenue and profit are favourable.

Split price from efficiency

Materials price = (actual price − standard price) × actual quantity. Materials efficiency = (actual quantity − standard quantity allowed for actual output) × standard price. Labour uses the same logic with hourly rates and hours. Selling-price variance uses actual sales volume. Fixed cost variance is actual fixed costs less flexible-budget fixed costs.

Worked example · Kaleidoscope glass

Actual glass = 7,100 × 1.3 = 9,230 lb. Standard allowed = 7,100 × 0.9 = 6,390 lb. Price variance = 9,230 × ($0.55 − $0.45) = $923 U. Efficiency variance = (9,230 − 6,390) × $0.45 = $1,278 U. Purchasing can investigate supplier terms and production can investigate waste. Check for shared causes such as input quality and treat each cause as a hypothesis.