Study notes
On this page
  1. Measure size and direction of errors
  2. When historical data is thin
  3. Explode the bill of materials
  4. Plan receipts, then offset releases

Session 2 · Forecast accuracy, BOM and MRP

Measure forecasting performance, distinguish independent and dependent demand, and time material orders.

Measure size and direction of errors

Use actual minus forecast for the course examples. Mean absolute error (MAE, also called MAD here) reports the typical error size in original units. MAPE averages absolute percentage errors and needs nonzero actuals. A tracking signal divides cumulative signed error by MAD. A positive signal indicates cumulative underforecasting under this sign convention. With errors +5, +5, −10 and +10, MAD is 7.5 units and the tracking signal is 10 ÷ 7.5 = 1.33. Compare with the exercise’s control limits.

When historical data is thin

Qualitative forecasts can draw on informed judgement when reliable time series are unavailable. The Delphi method gathers experts’ estimates in structured rounds and returns a summarized view for revision. Document assumptions and use an independent benchmark when feasible.

Explode the bill of materials

Independent demand comes from sales or the market. Dependent demand follows from the parent’s production plan. If 100 packs each require three labels, the plan creates gross demand for 300 labels. Use the parent’s planned order release timing when translating needs into component requirements.

Plan receipts, then offset releases

For each period, start from prior projected inventory, add scheduled receipts, subtract gross requirements and check safety stock. If inventory would fall short, determine net requirements, apply the lot-sizing rule to get a planned receipt, then offset it by lead time to find the planned release. Example: opening inventory 40, scheduled receipts 10, gross requirement 90 and safety stock 10 give a net need of 50. With lot-for-lot, plan a receipt of 50. If the requirement is in week 4 and lead time is two weeks, release the order in week 2. Verify that closing inventory is 10.